Uggh! What a tedious task. I have been at it for about eight hours (mostly in the evening). So many bolts, nuts, washers, nut plates… I am almost done, I think.
I honestly can’t figure out where a lot of this stuff will go. There are crazy amounts of very tiny nuts that I simply can’t envision where they will be used.
The hinge holds the upper cowling to the firewall. To remove the cowling, you pull the hinge pin out and the cowling can then be removed.
I have struggled with this seemingly easy step for a couple weeks. The instructions appear to have an error in them. The index holes that they call for do not line up with the holes in the firewall flanges and the top skin.
I also was concerned that the holes in the hinge that they call for in the instructions will be too close to the edge of the hinge. I have seen two different tolerances for edge distance: 2 diameters and 1.5 diameters (from the center of the hole to the edge). In this case, that would mean an edge distance of 3/8″ or 9/64″. My first attempt was a little shy of that smaller distance. Perhaps a more experienced builder would have ignored this and continued on but it bugged me.
While doing research on this topic I found Stu’s Aircraft Factory on Youtube. He built an RV-8. He has lots of interesting building tips. He mentioned in one video that the piano hinge supplied by Van’s is MS20257-3 and is susceptible to having broken knuckles (eyelets) over time. He recommended substituting MS20001P-3 extruded aluminum hinge. About 4x more expensive, but I decided to go with it since I had several broken knuckles on the RV-8 and RV-10 that I had owned.
I am confident in saying he was right and the added expense was worth it. Look at the difference between the two parts in the following pictures.
I spent about an hour putting the hinge on and match drilling it. I am happy with the result so far.
I picked it up at the ABF freight terminal this afternoon. No damage to the box. I found out that a friend of mine is the loading dock foreman there so he helped me get this BIG box onto the trailer (it just fit on the 5×10 U-Haul trailer). The only problem is that I had no way to unload it at the house other than to open it and remove all the parts. On perhaps the most windy day of the year I had packing paper flying everywhere.
Now the canopy and the back window plexi-glass are safely upstairs in the house where it is reasonably warm. The rest of the stuff is downstairs ready to be inventoried.
There were a few things on back order, but now I will be able to continue building for awhile.
Somehow when I installed it the NACA vent on the left side moved backward about half an inch. I didn’t notice it for a day or so and by that time the ProSeal had set up completely. My first inclination was to leave it as is and “repair” it with a bit of extra fiberglass. Jon and I discussed it and decided to remove the vent.
Using a safety knife and a carpet knife I was able to cut through most of the ProSeal to remove the vent. Unfortunately, during the process I had to destroy the vent itself.
I salvaged the eyeball part ($160) but will have to re-buy the fiberglass NACA vent which isn’t too expensive. I have about another hour of effort to remove the last of the ProSeal that is still on the inside of the fuselage skin.
The Whirlwind propeller arrived today and it is beautiful. I opened the box just to look at it despite not being able to do anything with it for at least three months.
Meanwhile, I got news that the finish kit will arrive at the freight terminal next Friday. It weighs 411 lbs and is 98″ x 49″ x 30″. The shipping charges were $770.00. If I had had it delivered to the house it would have cost an additional $70. I wasn’t sure when I was going to be home so I decided to just have it shipped to the terminal and then I can rent a trailer to go get it.
The panel is still being built at SteinAir. According to Nick, the panel has been cut and painted, but the technicians still have 4 to 5 panels in front of it. Still guessing it will be mid-April.
This was one of those rare days where things went smoothly with no mistakes, re-dos or other issues.
I got both sticks in. The cross connect is a bit challenging because there isn’t much room to work and there are washers and spacers that all have to be installed. I checked the alignment between the two sticks and the stick travel (fore and aft) and both were well within tolerance.
I then worked on the small Ray Allen sensor that is used to send the flap position to the EFISs and power controller. I was expecting this to be more difficult then it turned out to be. I had to remove part of the flap assembly that had been installed earlier so I could drill a hole in it but this was pretty straight forward. I still have to run the sensor’s wiring to the panel (when the panel arrives that is).
I got good news on the propeller and the interior. Both should ship in the next few days (a bit ahead of schedule). The finish kit should be in the crating process now so that should be coming in the next three weeks or so.
The instrument panel is being built at Steinair now (due in April-ish). The engine is likely to be mid May.
Jon and I have decided to remove the NACA vent that moved during install and redo it. Sucks, but in the end it will be better.
As usual a couple steps forward combined with a step or so backward.
We removed the airplane from the rotisserie (so we could access the firewall).
We worked on the stainless steel/fiberflax barrier for the firewall. This is designed to prevent a firewall forward fire from penetrating the cockpit. The challenge is that there are all kinds of penetrations that have to be cut out. Stuff like the master solenoid, the starter solenoid, the brake master cylinder, and various other components that are either mounted on the firewall or pass through the firewall.
There were also about 50 stainless steel rivets to install that hold the insulation “sandwich” to the aluminum firewall itself.
I installed the idler arms and linkages for the elevator control tubes. Not that difficult though I spent a fair amount of time getting washers and nuts all lined up in a fairly confined space.
I put the left stick together (twice since I initially had it backward) and installed it in the airplane. I will do the right stick next time I am in the workshop.
This is where I made my mistake that will require ordering more parts from Van’s. The top forward edge of the firewall has a piano hinge that is used to secure the back of the engine cowling. I carefully followed the directions but ended up with the holes too close to the edge of the hinge (I contend the plans have an error in them). The part is only $17 and I will add it to the finish kit which is being crated as we speak. Hopefully, I will have it in two weeks.
I also found an “oops” from a previous work session (NACA vent moved).
I got word that the Lycoming Thunderbolt engine that was originally supposed to arrive in March is now scheduled for May. Not too bad since I suspect I won’t be ready until late April anyway.
Propeller should be sooner. Also the interior (seats, stick boots, side panels etc.) should arrive from the manufacturer in Europe in about three weeks.
It is definitely starting to look like an airplane.
Jon stopped by to work on some more fuselage / tail interior items. We focused on completing the brake lines, installing the elevator control linkages and installing the pitch and yaw servos. We also ProSealed the NACA fresh air vent on the left side of the airplane. As usual we have another couple small items to order from Van’s Aircraft (total cost about $2 but shipping will be another $6).
I worked on the canopy hinges, gas struts and the canopy release mechanism. As usual, I put something together, tightened down bolts and then realized that I had missed a step and had to take it back apart. I have to wait for the paint to dry on one part of the canopy hinge mechanism so the total progress was miniscule.
I had planned to do some ProSeal work on the air vent today, but decided to put that off til tomorrow.